Twitter7 Dec RT @STAtimber: In Amsterdam, a new law has passed that we see all new housing projects from 2025 be constructed with at least 20% biobased…7 Dec The Government’s #BuildBackGreener document has set out plans and recommendations for how find a solution to the cl… https://t.co/1zMxeQd9Q17 Dec In Amsterdam, a new law has passed that we see all new housing projects from 2025 be constructed with at least 20%… https://t.co/zEKVN54fxW7 Dec RT @leadersmeets: For the UK to meet its legal target of Net Zero Carbon emissions by 2050, the construction industry needs to embrace the…

Youngs Homes, Snettisham

Stewart Milne Timber Systems - Residential Project

Stewart Milne Timber Systems’ innovative new build system, Sigma II, a fabric-first solution to create mass market Code Level Four homes, has been used to complete a development in Snettisham, Norfolk. The project consisted of 15 units of two-storey houses for Youngs Homes on behalf of Flagship Housing Developments. The aim was to achieve first-class energy saving insulation and air tightness, as well as cost-efficiencies in terms of offsite prefabrication. The solution they were looking for also had to be sufficiently adaptable to suit a variety of external finishes, window detailing and integration of services.

Project: Youngs Homes, Snettisham

Company: Stewart Milne Timber Systems

Sector: Residential

Technology: Timber Frame

Project Overview:
Stewart Milne Timber Systems’ innovative new build system, Sigma II, a fabric first solution to create mass market Code Level Four homes, has been used to complete a development in Snettisham, Norfolk.

The project consisted of 15 units of two-storey houses for Youngs Homes on behalf of Flagship Housing Developments. The aim was to achieve first-class energy saving insulation and air tightness, as well as cost-efficiencies in terms of offsite prefabrication. The solution they were looking for also had to be sufficiently adaptable to suit a variety of external finishes, window detailing and integration of services.

Project Type/Application:
Stewart Milne Timber Systems’ Sigma II product met these requirements through utilising space stud technology to vastly improve thermal bridging; and creating pre-insulated, closed external wall panels, filled with blown polystyrene beads,
which provide high thermal performance and 100 percent full fill of all voids within the panel. In addition a pre-formed service zone cavity on the internal face of the external walls allowed services to be easily fitted without cutting and notching.

Outcome / results / success factor

All 15 units were erected ahead of the five-week build programme. Subsequent inspection and testing of the erected units has confirmed the high level of accuracy of manufacture, panel fit and the incorporation of airtightness detailing measures.







Contact

If you would like to discuss a similar project, you can contact this member via their profile.

 